Bengaluru's Long-Delayed Ejipura Flyover Nears Completion

title

Time for Relief on City's Congested Roads

After nearly eight years of slow progress, the city's much-delayed Ejipura flyover project is finally moving at a brisk pace. With 60% of the construction now complete, BBMP has set an ambitious goal of completing the 2.5km flyover by the end of this year.


  • Key Points:
  • The contract was originally given to Simplex Infrastructure in 2017 but faced repeated delays and missed deadlines.
  • A new contractor, BSCPCL Pvt Ltd from Hyderabad, was awarded the remaining work with a 15-month timeline in November 2023.
  • The cost to complete the remaining construction is now set at Rs 176.1 crore, Rs 48 crore higher than the original estimate.
  • Detailed Analysis:

A Brief History of Delays

The Ejipura flyover project has been plagued by delays since its inception in 2017. Despite a contract deadline of Nov 2019, Simplex managed to finish only 42.8% of the project within five years. The urban development department eventually terminated the company's contract on March 3, 2022, and seized the security deposit of Rs 10.16 crore.

New Contractor Brings Hope

In November 2023, Hyderabad-based BSCPCL Pvt Ltd submitted a bid and was awarded the remaining work with a 15-month timeline. This change in contractor has brought new hope to the project's completion, with BBMP confident of delivering it by the end of this year.

Land Acquisition Remains a Challenge

One of the final challenges is the acquisition of 5,999 sq metres of land near St John's Medical College and hostel, required to complete the structure. "We are in discussions with the hospital authorities," said Raghavendra Prasad, chief engineer, quality control division, BBMP.

Impact on City's Congested Roads

The flyover aims to make seven major junctions signal-free, thereby significantly improving travel times across one of the most congested areas of the city. Upon completion, it will transform mobility across the Koramangala-Ejipura-Madivala corridor.


  • Conclusion:

After nearly eight years of delays and setbacks, Bengaluru's Ejipura flyover project is finally moving towards completion. With 60% of the construction complete and a new contractor on board, BBMP is confident of delivering it by the end of this year. The completion of this project will bring significant relief to commuters who travel through one of the city's most congested areas.

FacebookTwitterTelegram

Paying for Dates? Gen Z Has Opinions -- & They're Not What You'd Expect

A Generational Clash: Who Pays on a Modern Date?


Stallion's Name Out to be Made Proud in Lightning Stakes

Can an Obscure Pedigree Produce a Stakes Winner?


Senate Demand Probe into US Citizen Killed by Israeli Settlers

Pressure Mounts on Biden Administration Following Tragic Death in West Bank


Paramount and Skydance Merger Approved After Contentious Legal Battle

Hollywood Meets Politics: $8 Billion Deal Clears Final Hurdle


Trump Confronts Powell in Unprecedented Fed Visit, Backs Off Threat of Firing

A Rare Showdown Over Rates and Renovations


Kentucky Oaks Races into Primetime for 2026

A Twilight Shift for Horse Racing’s Beloved Tradition


Տուլի Տուիպուլոտուի առաջատար դիրքի բարձրացումը «Չարջերս»-ի պաշտպանության մեջ

Նորեկից մինչև ծագող աստղ. Տուիպուլոտուի աճող ազդեցությունը


Էպշտեյնի շաբաթ. Ուղեցույց՝ անպատիժ մնալու համար

Երբ մեղադրյալները դառնում են դատախազներ


Մեքենայի և կիսամեքենայի բախում. Դրամատիկ փրկարարական ջոկատ I-294 մայրուղում

Արագ արձագանքը փրկեց ուղևորներին վճարովի ճանապարհի հրդեհից